The Contractor shall be responsible for the true and proper sett

作者:高老师 浏览 1

The Contractor shall be responsible for the true and proper setting-out of the Works in relation to original points, lines and levels of reference given by the Engineer in writing and for the correctness,subject as abovementioned,of the position,levels,dimensions and alignment of all parts of the Works and for the provision of all necessary instruments, appliances and labor in connection therewith.
【正确答案】:承包商应负责按工程师书面提交的有关点、线和水平面的原始参数如实准确地进行工程放线,且如上所述,负责校准工程各部分的方位、水平、尺寸和定线,并负责提供一切必要的相关仪器、装置和劳力。
【题目解析】:p210