Schedule compression shortens the project schedule without chang

Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking

A.what-if scenario analysis

B.resource leveling

C.critical chain metho

正确答案是A